Status report of the n_TOF facility after the 2nd CERN long shutdown period

Research output: Contribution to journalArticlepeer-review

Abstract

During the second long shutdown period of the CERN accelerator complex (LS2,
2019-2021), several upgrade activities took place at the n_TOF facility. The most
important have been the replacement of the spallation target with a next generation
nitrogen-cooled lead target. Additionally, a new experimental area, at a very short
distance from the target assembly (the NEAR Station) was established. In this paper,
the core commissioning actions of the new installations are described. The
improvement in the n_TOF infrastructure was accompanied by several detector
development projects. All these upgrade actions are discussed, focusing mostly on
the future perspectives of the n_TOF facility. Furthermore, some indicative current
and future measurements are briefly reported.
Original languageEnglish
Article number13
Pages (from-to)1-10
Number of pages10
JournalEPJ Techniques and Instrumentation
Volume10
Issue number1
DOIs
Publication statusPublished - 17 May 2023

Keywords / Materials (for Non-textual outputs)

  • neutron time of flight
  • spallation target
  • nuclear astrophysics
  • neutron physics
  • neutron induced fission
  • neutron reactions